What action should be taken if one of the stages goes off track in PRINCE2?

The Project Manager should raise a Change Request

The Project Manager should raise an Exception Report to the Project Board

If one of the stages in a PRINCE2 project goes off track, the appropriate action is to raise an Exception Report to the Project Board. This is because an Exception Report is specifically designed to inform the Project Board about any significant deviations from the plan, particularly when performance is not meeting the tolerances set in the project initiation documentation. The report provides critical information about the situation, including the reasons for the issue, potential implications, and options for corrective actions. This allows the Project Board to make informed decisions on how to proceed, which may involve providing additional resources, adjusting plans, or authorizing changes to the project.

Using an Exception Report ensures that there is a formal communication channel between the Project Manager and the Project Board regarding project performance, maintaining governance and oversight over the project's progress. It is a key part of the PRINCE2 structured approach to managing projects and ensures clarity and accountability in addressing issues.

The Project Manager should consult the team for advice

The Project Manager should suspend the project immediately